Project Alerts
The tentative schedule for the 2023 Roadway Resurfacing Project is shown below. The schedule is weather dependent and subject to change.
Teaneck 2023 Roadway Resurfacing Program Schedule | ||||||
Street | From Street | To Street | Concrete Start | Concrete Finish | Milling | Paving |
Linden Ave | Hillcrest St | Bogota Border | 7/8/2024 | 7/12/2024 | 8/5/2024 | 8/7/2024 |
Cambridge Rd | Northumberland Rd | Dead End | 7/8/2024 | 7/12/2024 | 8/5/2024 | 8/7/2024 |
E. Laurelton Pkwy | Forest Ave | Emerson Ave | 7/10/2024 | 7/19/2024 | 8/5/2024 | 8/7/2024 |
Forest Ave | Windsor Rd | E. Laurelton Pkwy | 7/10/2024 | 7/19/2024 | 8/5/2024 | 8/7/2024 |
W. Laurelton Pkwy | Forest Ave | Dickerson Rd | 7/10/2024 | 7/19/2024 | 8/5/2024 | 8/7/2024 |
Sunderland Rd | Wilmerding Ave | Somerset Intersection | 7/16/2024 | 7/19/2024 | 8/6/2024 | 8/8/2024 |
Briarcliffe Rd | Wilbur Rd Intersection | 7/16/2024 | 7/19/2024 | 8/6/2024 | 8/8/2024 | |
Briarcliffe Rd | Rector Ct Intersection | 7/16/2024 | 7/19/2024 | 8/6/2024 | 8/8/2024 | |
Jefferson St | Maitland Ave | Winthrop Rd | 7/22/2024 | 7/26/2024 | 8/5/2024 | 8/7/2024 |
Intervale Rd | Teaneck Rd | Ardsley Court | 7/22/2024 | 7/26/2024 | 8/6/2024 | 8/8/2024 |
Walraven Dr | Hill St | Queen Anne Rd | 7/24/2024 | 7/30/2024 | 09/16/2024 | 09/18/2024 |
Genesee Ave | Teaneck Rd | Arlington Ave | 7/25/2024 | 7/31/2024 | 09/16/2024 | 09/18/2024 |
Darien Terr | Minell Pl | Audobon Rd | 7/29/2024 | 8/2/2024 | 09/16/2024 | 09/18/2024 |
E. Lawn Dr | Warren Pkwy | Dead End | 7/29/2024 | 8/2/2024 | 09/16/2024 | 09/18/2024 |
Sherwood Ave | Lees Ave | Teaneck Rd | 7/29/2024 | 08/02/024 | 09/17/2024 | 09/19/2024 |
Bryant Ave | Fycke Ln | Iris Ct | 8/5/2024 | 8/9/2024 | 09/17/2024 | 09/19/2024 |
Hemlock Terr North | Marion St | Glenwood Ave | 8/5/2024 | 8/16/2024 | 09/17/2024 | 09/19/2024 |